Projects

Bermversteviging-plaatsen-stalen-buizen

New verge reinforcement in Fridingen (DE)

Solines was commissioned to deliver a total of 260 steel pipes (approximately 110 tonnes) in the dimensions Ø 193.7 - 219.1 mm for a new verge reinforcement in Fridingen (DE). In order to be able to realize this construction, three different pipe diameters were required, which were partially welded...

stalen-meerpalen-voor-aanlegplaatsen-roeiboten-in-breda-worden-geplaatst - kopie

Over 300 berths around the city centre of Breda

One of our customers has been contracted by the Municipality of Breda to realize more than 300 berths in the canals around the city centre of Breda. The objective was to increase the quality of the canals in the recreational area. The berth consists of a pipe post 219.1...

Solines-levert-stalen-buizen-voor-paalwoningen

Solines supplies steel pipes for stilt houses.

For the construction of stilt houses, Solines supplied steel pipes in the diameter 244.5 mm and 406.4 mm. The unique thing about this project is that these luxury homes are really built in the middle of the water. For stability and strength, 200 metres of Ø 406.4 x 12.5 mm...

Stalen buizen voor de dek constructie voor ondergrondse garage

Roof construction for underground garage

Solines has supplied steel pipes for a new underground garage of a German insurer. For this project, 11 pipes with the diameter Ø 1220 x 10 mm were used for the underground garage. The pipes were part of the roof construction. Solines supplied the pipes, and a construction company was...

Verzinkte buizen voor tramlijn 23 in Rotterdam geleverd door Solines

Galvanized pipes for tram line 23 in Rotterdam

Tram line 23 runs through the Vakenoordseviaduct in Rotterdam. Between the Keizerswaard and Vuurplaat stops, the tramway for this line was renovated last June. To ensure that the distance between the duo blocks remained the same, the blocks were connected to galvanized pipes. Solines supplied galvanized pipes with a diameter...

Stalen buizen voor solide steigers in jachthavens

Steel pipes for solid jetties in marinas

Solines regularly supplies pipes for marinas. Recently, for a floating jetty of 150 metres in Wijk bij Duurstede. Often, the customer is looking for a suitable but above all affordable solution. Such a solution certainly cannot come at the expense of the quality of the total product: the jetty...

verzinkte_buizen-projecten

Steel construction: hot-dip galvanized pipes

For the construction of pig, cattle and chicken housing, use is made of thermally (dipped) galvanized pipes in different diameters. Among other things, Solines has a constant stock of galvanized pipes in Moerdijk, so that we can deliver directly. Pipes with different diameters and wall thicknesses These are pipes with diameters...

door Solines vervaardigde funderingspaal

Solines supplies pipes for a railway crossing

Solines supplied pipes for the foundation of traffic lights and barriers for a railway crossing. The unique thing about this project is that the foundation had to be placed in soil with very little bearing capacity. In order to guarantee the stability of the foundation, a hole was first drilled in...

Steel pipes for train washing line in Utrecht

Approximately 350 tonnes of pipes torch-cut to size Solines supplied steel pipes for the foundation of the concrete retaining wall for the new train washing line in Utrecht. Over two phases, we torch cut and delivered a total of approximately 350 tonnes of pipes in the dimension Ø 473 x...

152 metres of coated steel pipes for marina

For the placement of a mobile scaffolding, eight pipes had to be preserved all around over a length of 7.5 metres with a DTM (Direct To Metal) coating. The customer opted for black pipes (Ral 9017) with blue (Ral 5015) for the top 1.2 metres. For the best durability...

Marina is renovated with customized pipes

A marina in Noord-Holland bought 148 pipe piles in dimensions of Ø133 x 3.6mm. At the customer's request, various modifications were made to the pipes. For example, piles were welded together along their length, and strips, pile heads and foot plates were attached. The pipe piles were delivered at length...

Renovated Noorderbrug route pushes boundaries

In Maastricht, construction company Strukton Civiel demonstrated a fine example of civil engineering in the summer of 2017. A new, 180-metre-long bridge section of the Noorderbrug route will then be put in place all at once, including pillars and foundation. Solines supplied the steel pipes for the foundation piles...

Sunken N31 makes Harlingen one whole again

The N31 is the direct connection between Amsterdam and Leeuwarden. The road creates a division of Harlingen. By building a new road largely sunken, the visual division of Harlingen has vanished. In the new situation, the road crosses the Van Harinxmakanaal in the form of an aqueduct. Waiting times...

funderingspalen

Reconstruction of the Stompwijkseweg

The Stompwijkseweg is getting a new road surface over a length of about four kilometres; the bank construction is being partly replaced and partly renovated. To make the road more attractive for recreational traffic, there will be bicycle lanes on both sides. After completion of the work, the road can...

Piles for a dry dock in Katwijk

A foundation company was commissioned to realize the foundation of a waterproof cellar area in Katwijk. This will function as a dry dock for maintenance of yachts and small vessels. Solines supplied the steel pipes needed for this. 44 pile pipes with a diameter of 273 mm and a length...